"Demolish existing playground, sprayground, pool and related infrastructure. Build new playground, sprayground and restroom, including utilities, hardscape and landscape."
That is the Summary of Work in the City of Durham's project manual for Forest Hills Park Playground & Sprayground, dated November 3, 2026. The bid posting names only the playground and sprayground. The pool appears only in the scope. When this contract is done, the corner of the park by University Drive will have a new playground, a new sprayground and a restroom. The scope lists no new pool.
For a neighborhood whose 1920s plan put a pool on this same stretch of creek bottom, that's a real change. The details below cover how the park got here, why the sprayground has been dry since June, and what the contract says about the months ahead.
Durham Parks & Recreation's Forest Hills Park page tells the story. In the 1920s, businessmen James O. Cob and Fuller Glass, founders of the New Hope Realty Company, built the Forest Hills neighborhood out of farmland along Third Fork Creek. On the creek's floodplain they laid out a nine-hole golf course, a clubhouse and a pool.
The colonial revival clubhouse that still stands went up in 1928, replacing an original that burned. New Hope Realty went bankrupt in 1929, and John Sprunt Hill bought the golf course and clubhouse. In 1938 he deeded the land and building to the City on the condition that it serve as a public library. In the early 1950s the building became a community center.
The golf course is long gone, but the clubhouse and a pool lasted into the modern park. In June 2025, DPR's announcement of outdoor pools for summer 2025 listed Forest Hills Pool at 1639 University Drive as one of its two seasonal outdoor pools, scheduled to open June 4 and close for the season August 9. The Forest Hills sprayground at the same address was also on the summer list. The new contract removes the pool, while the clubhouse the City acquired in 1938 stays at the center of the plan.
Families who walked over this summer found the sprayground closed, and the reason is citywide. Durham moved to a Stage 2 Water Shortage Response on Monday, June 15, 2026, because of extreme drought. Water levels had dropped at the City's two reservoirs, Lake Michie and Little River Reservoir.
The City's June 11 announcement explained the park impact directly. All DPR spraygrounds use nonrecirculating water, so they "cannot operate under Stage 2" and were "closed until further notice." DPR's indoor pools and its one outdoor pool could keep running and be topped off as needed, but not fully refilled. On the same page, DPR said it would keep watering landscaping and athletic fields, cutting field watering to two days a week and converting its water tanks to reclaimed water.
Five months later, the City's November 2 update says Stage 2 is still in effect. As of November 1, combined lake storage was at 33 percent, and the City estimated 83 days of easily accessible supply. Spray irrigation of landscapes with City water is still prohibited. Drip irrigation, hand watering and tree watering bags are among the listed exceptions. The June announcement adds that hand watering needs a hose attachment with automatic shutoff, and that Stage 2 lasts until both reservoirs are full again. That rule matters for the mature oaks and established gardens on the streets around the park. The full list of measures and FAQs is at DurhamNC.gov/1061. This is a summary of published City rules, not legal advice, so check your own property's situation with the City's Water Management Department.
Once construction is finished, the sprayground will be the park's only summer water feature, and it's the same feature Stage 2 has kept dry since mid-June.
The project has been in the City's capital plan for several years. The FY 2024-25 capital ordinance lists Forest Hills Park Playground and Sprayground, project CH485, at $1,293,750. Of that, $1,250,000 comes from Zone 1 Parks & Recreation impact fees, and $43,750 is a transfer from the Debt Service Fund.
By the City's FY 2025-26 third-quarter project report, the "Forest Hills Park Play & Spray" project was 30 percent through design, and the schematic design had been revised after DPR input. The November 3 bid documents are the next step: a full construction package with civil, landscape, architectural and electrical sheets, published by the General Services Department.
The project is in procurement now. These are the dates the City has published:
The 275 days count from the notice to proceed, not from the bid deadline. The calendar fills in once the City picks a contractor and issues that notice.
For neighbors, the most useful part of the bid package is buried in the technical specifications, in a section called Contractor's Use of Premises. It shows the City wrote the contract around the park staying in use.
These rules protect the times most visitors use the park and the 1928 clubhouse that hosts events. Weekday daytime is when the contractor will have the most room to work.
The pool and sprayground were seasonal anyway, and the rest of the park sits outside the playground corner. DPR's park page lists these features:
| Feature | Details from DPR |
|---|---|
| Tennis courts 1 to 3 | Lined for adult tennis plus 10-and-under and 8-and-under play |
| Court 4 | The first outdoor DPR site to offer pickleball lines |
| Tennis backboard | Listed among park features |
| Picnic shelter | Rentable through DPR's picnic shelter rentals page |
| Greenway and trail access | Listed among park features |
| Grill, picnic tables, water fountain | Listed among park features |
Courts can also be reserved through DPR's athletic rentals page.
The park's holiday-season calendar is mostly contractors and paperwork, so downtown Durham, a short drive north, has the events. Discover Durham's holiday events guide lists:
The parade falls two days after the December 10 bid deadline. By then the City will have the contractor bids that decide when work starts at Forest Hills Park.
We'll keep watching the Forest Hills Park bid as it moves from the December 10 deadline toward a contract award. If you have questions about how this project or other changes in Durham might affect your plans, The May Team would be glad to talk them through with you. Contact Us.
A handful of nearby trails give you the same late-season color from solid ground.